F-35 Program Production Costs Rise $7.4 Billion

Pratt and Whitney F-135 engineThe cost to develop and build the Joint Strike Fighter fleet rose 1.88 percent over the past year because of delays in the production line and failures of the engine producer to bring down costs, said Lt. Gen. Chris Bogdan, F-35 Program Executive Officer.

The cost of the program rose by $7.4 billion to $398.58 billion in 2012-year dollars, according to the Pentagon’s Selected Acquisition Report that is released each year to Congress. The increase in costs means tax payers will end up paying $162 million for each fifth generation fighter jet by the end of the program at the current rate.

Bogdan blamed the increased costs on the decision to push back production of the F-35 and failures by Pratt and Whitney, the company building the fighter jet’s engine. The costs of the JSF engine increased by $4 billion, Bogdan said.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.